Dismantling, transport and relocation of 126 machines to a new site

Dismantling, transport and relocation of 126 machines to a new site, as well as positioning and levelling them in their designated location, as specified by the customer. We were contracted to move and transport 126 machine units out of a hall, relocate them into a hall at the customer’s new site, then to level and position them in place. The timing of the relocation was coordinated with the customer, as the customer’s former leased premises continued production throughout the relocation.
Dismantling, transport and relocation of 126 machines to a new site

To move out the larger machine units, the hall doors had to be widened, which required structural design and the construction of supports. The machines were moved from a ramp onto the transport vehicles using a stepping procedure. In many cases, the overhanging lean-to made it difficult to lift the machines onto the transport vehicle.

Another challenge was that the power supply to the hall had not been fully installed and the access road was too narrow when the first machines arrived at the new site, so we worked with the customer to build turning islands to ensure safe working conditions. Inside the hall, the power rails were typically low, so we had to work with the customer to redesign the paths the machines would take (sometimes increasing them 300% more than planned), and the final positioning of the larger machine units.

The job was completed on time and to the customer’s complete satisfaction.