Dismantling a service crane

We lifted two bridges, which each weighed 18 tonnes and measured 24 m long and 14 m high. We used our 60-tonne truck crane to do this and then we rolled them out. The bridge sections had been out of service for a long time, so moving them to the lifting location took some time. To release the cranes and lower them to the ground, we had to remove the fixing shafts from the four trolleys on the track.
Dismantling a service crane

The fixing shafts were rusted and tight, so we used a knock-out tool and a sledgehammer to knock them out of the bushing, which took a long time. A complicating factor during the project was that there was a deep tunnel at one of the locations we had to lift the overhead crane from. In fact it was right under our 60-tonne truck crane, so we had to make sure that the crane’s jacks were resting on the load-bearing column in the basement. There was no information available on the weight of the overhead cranes, so we had to estimate their weight based on their size and material. There was no lifting point on the overhead cranes either, so we had to install one ourselves, bearing in mind that when the crane lifted off the track, it would be just our 60-tonne truck crane holding it. Despite the many challenges, the project was successfully completed to the customer’s satisfaction.


Széchenyi Pályázat 2020
Request offer